Construction Calendar

on our New House

- 27 July 2000 - 11 April 2002

AUGUST 2000
21 - 

Days - 31, WE Days - 8 (Sch'd WE Work Days + 4), Available Days - 27, Work days - 20, Lost Work Days - 6,
Inspection Days - 1

SUNDAY
MONDAY
TUESDAY
WEDNESDAY
THURSDAY
FRIDAY
SATURDAY
1
LWD-44
2
Insulation Inspection 
REJECTED
3
LWD-45
4
Recpt. for security system panel roughed-in
Insulation Insp
PASSED
Work Day-44
5
6
7
LWD-46
8
LWD-47
9
Doors Hung
& Hanging Drywall
Work Day-45
10
Hanging Drywall
Work Day-46 
Early Compln
$--$
(Missed)
11
Hanging Drywall
Work Day-47
12
Drywall Hanging
Completed

Work Day-48

13
14
Drywall - Taping
& Mudding
Work Day-49
15
LWD-48
16
Drywall finishing
Work Day-50
17
Drywall finishing
Work Day-51
18
Drywall finishing
Work Day-52
19
Drywall finishing
completed
Work Day-53
20
21
Drywall - Ceiling Texture
Work Day-54
22
LWD-49
"Fixin' to Day"
23
Interior Trim
Doors & Molding
Work Day-55
24
Interior Trim
Doors & Molding
Work Day-56
25
Interior Painting
Work Day-57
26
Interior Painting
Work Day-58
27
Interior Painting
Work Day-59
28
Soffit & Facia
Work Day-60
29
Soffit & Facia
HVAC
Work Day-61
30
Soffit & Facia
Work Day-62
31
Prep Floor
for Tile
Elec Trim
Work Day-63
 



 
 
 


August 1 - Insulation

August 1 - Insulation

August 1 - Ext doors, 2of 3 "ok"
(Front porch to BR Door s/b 1/2 glass)

August 3 - Insulation 
Sound barrier, relocated to Kitchen wall

August 9 - framing for front porch sliding door & window

August 9 - Front door, sidelites, & Transom set

August 11 - Hanging drywall

August 11 - Hanging drywall

August 18 - Drywall finishing
Tape, mud, & sand

August 19 - Drywall finishing

August 21 - Spray apply ceiling texture
"California knockdown"

August 23 - Interior trim, doors & baseboards

August 23 - Interior trim, doors & baseboards

August 26 - Interior painting

August 26 - Interior painting
(Chair rail & cap molding/shelf in Dining Room)

August 26 - Shelving added in storage shed
(Porch railing stored 'till "later")

August 29 - Applying Aluminium Soffit & Facia

August 29 - Applying Aluminium Soffit & Facia
A/C - outside unit set

August 29 - H&A/C AHU

August 31 - Soffit & Facia at front

August 31 - Tile materials
 