Construction Calendar

on our New House

- 29 September 2000 - 11 April 2002

OCTOBER 2000
23 - 

(Plus 6  from our House warming party
Rework (ponds) at entry & Flagpole addition

Days - 31, WE Days - 9 (Sch'd WE Work Days + 1), Holidays - 0, Available Days - 23, Work days - 14,
Lost Work Days - 2, Inspection Days - 0

SUNDAY
MONDAY
TUESDAY
WEDNESDAY
THURSDAY
FRIDAY
SATURDAY
1
2
Kitchen Counter
Backsplash Tile

Work Day-88

3
Electrical 
Check-out

Work Day-89

4
Electrical
Check-out
HVAC
Check-out
Rework
MedCab RO's

Work Day-90

5
Tile completed
Elec. completed
Power pulled
to back
Garage Door
Installed
HVAC 
Check-out

Work Day-91

6
Carpet Installed
Doors Trimmed
Range & Fridge
Moved inside

Work Day-92

Late Compln
week +5
7
8
9
Pre-clean
Phones connected

Work Day-93

10
Plumbing check-out
Pergo Flooring

Work Day-94

11
PL work off

Final Grading
Install Final Filter
Pre Clean

Work Day-95

12
PL work off

Painting
PL work-off
Gutters Installed

Work Day-96

13
PL work-off

Pergo & plumber

Work Day-97

Late Compln
week +6
14
Sod

Work Day-98

15
16
Install Railings
Final cleaning

Work Day-99

House
FINAL
Passed
Health Dept
FINAL
Passed
17
Punchlist Work

Work Day-100

Driveway
FINAL
Passed
18

LWD-50

19

LWD-51

CO
ISSUED
20
Punchlist Work

Work Day-101

21
22
23
MOVING 
DAY
24
25
26
27
28
29
30
31
       



Oct 2 - Kitchen, Tile counter backsplash

Oct 3 - We've got LIGHTS !!!

Oct 5 - rinning power to Garage, Well, & Storage Shed

Oct 5 - Garage (Shop) Door

Oct 6 - Laying carpet

Oct 6 - Laying carpet

Oct 6 - Install Kitchen appliances

Oct 8 - Garage (Shop) door

Oct 8 - New doors on (old) Garage

Oct 11 - final grading / prep for Sod

Oct 11 - Pergo floor - desk area in MBR

Oct 11 - (re)work tub skirt to be removable

Oct 11 - installing Culligan's Final / Triple Filter

Oct 13 - Gutters & downspouts

Oct 14 - Washroom appliances & tub for "The Boz"

Oct 14 - Laying Sod

Oct 14 - Laying Sod

Oct 14 - "All over but the shouting"

Oct 14 - HAPPY DAD !!!

Oct 14 - HAPPY RICK !!! 
Taaa - Daaaa

Oct 16 - Railing at main (rear) entry porch

Oct 16 - railing at front / river porch steps

 

OCTOBER 23,2001 - MOVING DAY !!!!


House Warming & Rework (ponds & watergardens) at entry



 


Nov 4 - House Warming

Nov 4 - House Warming

Feb 2 2001 - Reworked entry, added ponds & river rock