Construction Calendar on our New House

- 30 May 2000 - 11 April 2002
APRIL 2000
3 - 

Days - 30, WE Days - 10*, Available Days - 21*, Work days - 2, Lost Work Days - 18, Inspection Days - 1
(*Work was "scheduled" for Saturday, 29 April)

SUNDAY
MONDAY
TUESDAY
WEDNESDAY
THURSDAY
FRIDAY
SATURDAY
     
1
WE-1
2
WE-2
3
No Work
LWD-4
Permits picked
up today
4
No Work
LWD-5
5
No Work
LWD-6
6
No Work
LWD-7
7
No Work
LWD-8
8
WE-3
9
WE-4
10
No Work
LWD-9
11
No Work
LWD-10
12
No Work
LWD-11
13
No Work
LWD-12
14
No Work
LWD-13
15
WE-5
16
WE-6
17
No Work
LWD-14
18
Stem Wall footers
4 x ~ 6 hr
Work Day-1 
Footer
Inspection
PASSED
19
Insp Day-1
20
Stem Wall Footers
2 x 4 Hr
2 x 2 Hr
Work Day-2
21
No Work
LWD-15
22
WE-7
23
WE-8
24
No Work
LWD-16
25
No Work
LWD-17
26
No Work
LWD-18
27
No Work
LWD-19
28
No Work
LWD-20
29
Work "Scheduled"
for Stem Wall Blockwork
No Work
WE-9
LWD-21
30
WE-10
           



April 19 - Footing Reinforcement

April 19 - Footing Reinforcement

April 20 - Place Footings
 