Days - 30, WE Days - 10*, Available Days
- 21*, Work days - 2, Lost
Work Days - 18, Inspection Days - 1
(*Work was "scheduled" for Saturday, 29 April)
|
|
|
|
|
|
|
|
WE-1 |
|||||||
WE-2 |
No Work LWD-4 Permits picked up today |
No Work LWD-5 |
No Work LWD-6 |
No Work LWD-7 |
No Work LWD-8 |
WE-3 |
|
WE-4 |
No Work LWD-9 |
No Work LWD-10 |
No Work LWD-11 |
No Work LWD-12 |
No Work LWD-13 |
WE-5 |
|
WE-6 |
No Work LWD-14 |
Stem Wall footers 4 x ~ 6 hr Work Day-1 |
Insp Day-1 |
Stem Wall Footers 2 x 4 Hr 2 x 2 Hr Work Day-2 |
No Work LWD-15 |
WE-7 |
|
WE-8 |
No Work LWD-16 |
No Work LWD-17 |
No Work LWD-18 |
No Work LWD-19 |
No Work LWD-20 |
Work "Scheduled" for Stem Wall Blockwork No Work WE-9 LWD-21 |
|
WE-10 |
April 19 - Footing Reinforcement |
April 19 - Footing Reinforcement |
April 20 - Place Footings |