MAY 2000
13 -
Days - 31, WE Days - 8, Holiday - 1, Available Days - 22, Work days - 10, Lost Work Days - 12, Inspection Days - 0
|
|
|
|
|
|
|
|
No Work LWD-22 |
Stem Wall Blockwork 8 x ~ 3 1/2 hr Work Day-3 |
Stem Wall Conc Fill 2 x ~ 2 hr Work Day-4 |
No Work LWD-23 |
No Work LWD-24 |
WE-11 |
||
WE-12 |
Sub slab fill 1 x ~ 2 hr Work Day-5 |
Sub slab fill 1 x ~ 3 hr 1 x ~1 hr Work Day-6 |
Sub slab fill 1 x ~4 hr 2 x ~ 1 1/2 hr Work Day-7 |
No Work LWD-25 |
No Work LWD-26 |
WE-13 |
|
WE-14 |
No Work LWD-27 |
Pre Rough-in Formwork 3 x ~4 hr Work Day-8 |
Plumbing Rough-in 2 x ~ 4 hr Work Day-9 |
No Work LWD-28 |
No Work LWD-29 |
WE-15 |
|
WE-16 |
No Work LWD-30 |
Slab Prep 3 x ~8 hr 1 x ~1 hr Work Day-10 |
Slab prep 2 x ~ 4 1/2 Work Day-11 |
Main Slab & Garage Placement 3 x ~9 hr 2 x 5 hr 1 x 4 hr Work Day-12 |
No Work LWD-31 |
WE-17 |
|
WE-18 |
Holiday - 1 |
No Work LWD-32 |
No Work LWD-33 |
May 2 - Lay Block "Stem" (Foundation) Walls |
May 3 - Concrete fill, Stem walls |
May 10 - Backfill for Slab |
May 16 - Form Slab & Porch recesses |
May 16 - Form Slab & Porch recesses |
May 17 - Under slab plumbing rough-in |
May 23 - Slab prep, layout & excavate for bearing walls |
May 23 - Slab prep, layout & excavate for bearing walls |
May 23 - Slab prep, layin moisture barrier |
May 24 - (re)form front porch recess |
May 25 - Place slab |
May 25 - Place slab |
May 25 - Place slab |