Construction Calendar

on our New House

- 30 May 2000 - 11 April 2002

JUNE 2000
18 - 

Days - 30, WE Days - 8, Available Days - 22, Work days - 11, Lost Work Days - 10, Inspection Days - 1

SUNDAY
MONDAY
TUESDAY
WEDNESDAY
THURSDAY
FRIDAY
SATURDAY
1
No Work
LWD-34
2
No Work
LWD-35
(Block matls delivered)
3
WE-19
4
WE-20
5
No Work
LWD-36
6
No Work
LWD-37
7
No Work
LWD-38
8
Exterior Wall
Blockwork
Work Day-13
9
Exterior Wall
Blockwork
Work Day-14
10
WE-21
11
WE-22
12
Exterior Wall
Blockwork
Work Day-15
Bond Beam
PrePour
Inspection
PASSED
13
Inspection Day
#2
14
Bond Beam Prep
Work Day-16
15
Truss Strap
Layout
Work Day-17
16
Pour 
Bond Beam Work Day-18
17
WE-23
18
WE-24
19
No Work
LWD-39
20
No Work
LWD-40
Trusses Delivered
21
No Work
LWD-41
22
No Work
LWD-42
23
No Work
LWD-43
24
WE-25
25
WE-26
26
Framing
Work Day-19
27
Framing
Work Day-20
28
Set Trusses
Work Day-21
29
Align Trusses
Set corners
Work Day-22
30
Align Trusses
set hips & valleys
Work Day-23



June 8 - Blockwork

June 8 - Blockwork

June 9 - Set lintels & cap block

June 9 - Set wall reinforcement / cap block ties

June 9 - Front view looking NNW

June 12 - Blockwork complete

June 17 - Cap block / bond beam poured w/ roof tie straps

June 20 - layout for interior walls

June 21 - Dad looks over the roof trusses delivered

June 26 - "Shake out" Roof Trusses

June 26 - build bearing walls

June 28 - Setting roof trusses

June 28 - Setting roof trusses

June 28 - Setting roof trusses

June 28 - Setting roof trusses

June 28 - Setting roof trusses

June 29 - completing hips & tails

June 29 - roofing materials delivered