JUNE 2000
18 -
Days - 30, WE Days - 8, Available Days - 22, Work days - 11, Lost Work Days - 10, Inspection Days - 1
|
|
|
|
|
|
|
|
No Work LWD-34 |
No Work LWD-35 (Block matls delivered) |
WE-19 |
|||||
WE-20 |
No Work LWD-36 |
No Work LWD-37 |
No Work LWD-38 |
Exterior Wall Blockwork Work Day-13 |
Exterior Wall Blockwork Work Day-14 |
WE-21 |
|
WE-22 |
Exterior Wall Blockwork Work Day-15 |
Inspection Day #2 |
Bond Beam Prep Work Day-16 |
Truss Strap Layout Work Day-17 |
Pour Bond Beam Work Day-18 |
WE-23 |
|
WE-24 |
No Work LWD-39 |
No Work LWD-40 Trusses Delivered |
No Work LWD-41 |
No Work LWD-42 |
No Work LWD-43 |
WE-25 |
|
WE-26 |
Framing Work Day-19 |
Framing Work Day-20 |
Set Trusses Work Day-21 |
Align Trusses Set corners Work Day-22 |
Align Trusses set hips & valleys Work Day-23 |
June 8 - Blockwork |
June 8 - Blockwork |
June 9 - Set lintels & cap block |
June 9 - Set wall reinforcement / cap block ties |
June 9 - Front view looking NNW |
June 12 - Blockwork complete |
June 17 - Cap block / bond beam poured w/ roof tie straps |
June 20 - layout for interior walls |
June 21 - Dad looks over the roof trusses delivered |
June 26 - "Shake out" Roof Trusses |
June 26 - build bearing walls |
June 28 - Setting roof trusses |
June 28 - Setting roof trusses |
June 28 - Setting roof trusses |
June 28 - Setting roof trusses |
June 28 - Setting roof trusses |
June 29 - completing hips & tails |
June 29 - roofing materials delivered |