Days - 31, WE Days - 10, Holidays - 1, Available Days - 20, Work days - 20, No Work Days - 0, Inspection Days - 0
|
|
|
|
|
|
|
|
WE-25 |
|||||||
WE-26 |
Sub-Facia Work Day-24 |
4 Holiday-2 |
Roof Decking Work Day-25 |
Roof Decking Work Day-26 |
Roof Deck final nailing & dry-in Work Day-27 |
WE-27 |
|
WE-28 |
Int. Framing Work Day-28 |
Int. Framing Work Day-29 |
Int Framing Work Day-30 |
Int Framing & A/C Ducts Work Day-31 |
Set Windows Furr Windows Set Int Pkt Door Frames Support Trades Plumb TopOut A/C Ducts A/C Drain A/C Gas Piping Work Day-32 |
WE-29 |
|
WE-30 |
Int Framing Elec Rough in Work Day-33 |
Framing Complete (Except Doors) Elec Rough in Work Day-34 |
Elec Rough-in Work Day-35 |
Elec Rough-in & Question resolution Work Day-36 |
Mba Tub delv Whirlpool kit installed Work Day-37 |
WE-31 |
|
WE-32 |
Plumb MBa tub Elec Rough in Work Day-38 |
Plumbing: Air Preas. ck Grout drains Elec Rough in Work Day-39 |
Pour Porches Work Day-40 |
Rough in Security System Work Day-41 |
Roofing completed Drywall matl delivered Work Day-42 |
WE-33 |
|
WE-34 |
Insulation Prep Work Day-43 |
July 3 - Trimming Tails & running soffit |
July 5 - Roof decking |
July 5 - Roof decking |
July 6 - Roof decking |
July 6 - Roof decking |
July 6 - Roof decking |
July 7 - Roof, "dry-in" |
July 10 - Interior partitions |
July 11 - Interior partitions |
July 11 - Interior partitions |
July 12 - Windows delivered |
July 12 - "strapping" trusses @ bearing walls |
July 13 - final visit to approve cabinet order |
July 13 - A/C ductwork |
July 13 - A/C Return air plenum |
July 14 - setting windows |
July 14 - Plumbing "top-out" |
July 14 - Plumbing "top-out" |
July 17 - Electrical rough-in |
July 18 - framing front door & archways |
July 18 - Electrical rough-in |
July 18 - Electrical rough-in |
July 19 - Electrical rough-in, landing @ main panel |
July 21 - tub delivered & set in place |
July 26 - placing tinted concrete @ front (East) porch |
July 26 - placing tinted concrete @ back (West) porch |
July 27 - Security system rough-in |
July 28 - delivering drywall materials |
July 28 - roofing, flashing @ valleys |
July 28 - flashing valleys & "Cricket" over garage |
July 28 - "Cricket" at intersection of 3 roof slopes |
July 28 - Roofing |
July 31 - sheetrock materials - "next" |
July 31 - sheetrock materials - "next" |