Construction Calendar on our New House

- 30 June 2000 - 11 April 2002
JULY 2000
34 - 

Days - 31, WE Days - 10, Holidays - 1, Available Days - 20, Work days - 20, No Work Days - 0, Inspection Days - 0

SUNDAY
MONDAY
TUESDAY
WEDNESDAY
THURSDAY
FRIDAY
SATURDAY
     
1
WE-25
2
WE-26
3
Sub-Facia
Work Day-24
Independance. Day
4
Holiday-2
5
Roof Decking
Work Day-25
6
Roof Decking
Work Day-26
7
Roof Deck
final nailing 
& dry-in
Work Day-27
8
WE-27
9
WE-28
10
Int. Framing
Work Day-28
11
Int. Framing
Work Day-29
12
Int Framing
Work Day-30
13
Int Framing
& A/C Ducts
Work Day-31
14
Set Windows
Furr Windows
Set Int Pkt Door Frames
Support Trades
Plumb TopOut
A/C Ducts
A/C Drain
A/C Gas Piping
Work Day-32
15
WE-29
16
WE-30
17
Int Framing
Elec Rough in
Work Day-33
18
Framing Complete
(Except Doors)
Elec Rough in
Work Day-34
19
Elec Rough-in
Work Day-35
20
Elec Rough-in
& Question resolution
Work Day-36
21
Mba Tub delv 
Whirlpool kit installed
Work Day-37
22
WE-31
23
WE-32
24
Plumb MBa tub
Elec Rough in
Work Day-38
25
Plumbing:
Air Preas. ck
Grout drains
Elec Rough in
Work Day-39
Frame All
Inspection
PASSED
26
Pour Porches
Work Day-40
27
Rough in
Security System
Work Day-41
28
Roofing completed
Drywall matl delivered
Work Day-42
29
WE-33
30
WE-34
31
Insulation Prep
Work Day-43
         



July 3 - Trimming Tails & running soffit

July 5 - Roof decking

July 5 - Roof decking

July 6 - Roof decking

July 6 - Roof decking

July 6 - Roof decking

July 7 - Roof, "dry-in"

July 10 - Interior partitions

July 11 - Interior partitions

July 11 - Interior partitions

July 12 - Windows delivered

July 12 - "strapping" trusses @ bearing walls

July 13 - final visit to approve cabinet order

July 13 - A/C ductwork

July 13 - A/C Return air plenum

July 14 - setting windows

July 14 - Plumbing "top-out"

July 14 - Plumbing "top-out"

July 17 - Electrical rough-in

July 18 - framing front door & archways

July 18 - Electrical rough-in

July 18 - Electrical rough-in

July 19 - Electrical rough-in, landing @ main panel

July 21 - tub delivered & set in place

July 26 - placing tinted concrete @ front (East) porch

July 26 - placing tinted concrete @ back (West) porch

July 27 - Security system rough-in

July 28 - delivering drywall materials

July 28 - roofing, flashing @ valleys

July 28 - flashing valleys & "Cricket" over garage

July 28 - "Cricket" at intersection of 3 roof slopes

July 28 - Roofing

July 31 - sheetrock materials - "next"

July 31 - sheetrock materials - "next"