AUGUST 2000
21 -
Days - 31, WE Days - 8 (Sch'd WE Work Days + 4),
Available Days - 27, Work days - 20, Lost
Work Days - 6,
Inspection Days - 1
|
|
|
|
|
|
|
||
LWD-44 |
Insulation Inspection
|
LWD-45 |
Recpt. for security system panel roughed-in
|
|
||||
|
LWD-46 |
LWD-47 |
Doors Hung & Hanging Drywall Work Day-45 |
Hanging Drywall Work Day-46 |
$--$ (Missed) 11 Hanging Drywall Work Day-47 |
Drywall Hanging Completed Work Day-48 |
||
|
Drywall - Taping & Mudding Work Day-49 |
LWD-48 |
Drywall finishing Work Day-50 |
Drywall finishing Work Day-51 |
Drywall finishing Work Day-52 |
Drywall finishing completed Work Day-53 |
||
|
Drywall - Ceiling Texture Work Day-54 |
LWD-49 "Fixin' to Day" |
Interior Trim Doors & Molding Work Day-55 |
Interior Trim Doors & Molding Work Day-56 |
Interior Painting Work Day-57 |
Interior Painting Work Day-58 |
||
Interior Painting Work Day-59 |
Soffit & Facia Work Day-60 |
Soffit & Facia HVAC Work Day-61 |
Soffit & Facia Work Day-62 |
Prep Floor for Tile Elec Trim Work Day-63 |
August 1 - Insulation |
August 1 - Insulation |
August 1 - Ext doors, 2of 3 "ok" (Front porch to BR Door s/b 1/2 glass) |
August 3 - Insulation Sound barrier, relocated to Kitchen wall |
August 9 - framing for front porch sliding door & window |
August 9 - Front door, sidelites, & Transom set |
August 11 - Hanging drywall |
August 11 - Hanging drywall |
August 18 - Drywall finishing Tape, mud, & sand |
August 19 - Drywall finishing |
August 21 - Spray apply ceiling texture "California knockdown" |
August 23 - Interior trim, doors & baseboards |
August 23 - Interior trim, doors & baseboards |
August 26 - Interior painting |
August 26 - Interior painting (Chair rail & cap molding/shelf in Dining Room) |
August 26 - Shelving added in storage shed (Porch railing stored 'till "later") |
August 29 - Applying Aluminium Soffit & Facia |
August 29 - Applying Aluminium Soffit & Facia A/C - outside unit set |
August 29 - H&A/C AHU |
August 31 - Soffit & Facia at front |
August 31 - Tile materials |