SEPTEMBER 2000
58 -
Days - 30, WE Days - 9 (Sch'd WE Work Days + 4),
Holidays
- 1, Available Days - 24, Work days - 24,
Lost Work Days - 0, Inspection
Days - 0
|
|
|
|
|
|
|
||||
Wall Prep Tile Prep Elec. Trim Work Day-64 |
Tile Work Work Day-65 |
|||||||||
|
4 Holiday-3 |
Tile Work Work Day-66 |
Stucco Prep Work Day-67 |
Stucco Work Tile Work Elec Trim Work Day-68 |
Stucco Work Tile Work Elec Trim Driveway prep Work Day-69 |
Stucco Work Work Day-70 |
||||
|
Blow Insul. Elec Trim Water Lines Work Day-71 |
Stucco Finish (N&W) Install Cab's Work Day-72 |
Grout Bath Tile Elec Trim Work Day-73 |
Asphalt removal Septic T&DF install Work Day-74 |
Septic T&DF Rough Grade Work Day-75 |
Finish Doors Work Day-76 |
||||
|
Plumbing Trim Marble Work Tile Work Elec Trim Shelving Work Day-77 |
Elec Trim Work Day-78 |
Stucco Work completed Misc. Carpentry Work Day-79 |
Driveway Form Counter Top "Template" Work Day-80 |
Final Grade Driveway (backend) Work Day-81 |
Driveway form (front end) Work Day-82 |
||||
|
25
|
Driveway Placement Ba2 Shower Curb Cap Work Day-84 |
Driveway Placement Counter Tops Wire Shelving Shower Encosures Plumbing Trim Work Day-85 |
Front Porch Screen-in Work Day-86 |
Gale - mirrors Tryon - Plumbing Trim FP&L
Work Day-87 |
|
LOTS OF PICTURES ... Then again, a LOT finally "came together" this month !!
Sept 2 - Tile setting, Entry Foyer |
Sept 2 - Tile setting, Kitchen & Dining Nook |
Sept 2 - Tile setting, Kitchen |
Sept 7 - Electrical "Trim", Installed Lights 1st up - the Ships Wheel Chandelier, salvaged from Dad & Mom's house (from "nearly" the same position) |
Sept 7 - Electrical "trim", Installed ceiling fans & lights |
Sept 7 - Stucco, "scratch coat" |
Sept 7 - Tile setting, Bath 2 |
Sept 7 - Tile setting, Master Bath |
Sept 8 - Stucco, scratch coat |
Sept 8 - stucco, scratch coat (& electrical conduit runs to Garage & Storage Shed) |
Sept 11 - plumbing, run supply from well |
Sept 11 - plumbing, run supply from well |
Sept 11 - plumbing, run supply from well |
Sept 13 - Kitchen cabinets hung |
Sept 13 - Kitchen cabinets hung |
Sept 11 - Electrical trim, outside lights |
Sept 11 - Electrical trim, meter box & main disconnect |
Sept 14 - remove old asphalt drive |
Sept 14 - deliver septic tank |
Sept 14 - driveway removal |
Sept 14 - set septic tank1 |
Sept 14 - driveway removal |
Sept 14 - driveway removal |
Sept 14 - septic drainfield installation |
Sept 15 - septic drain field installation |
Sept 15 - septic drain field installation |
Sept 15 - grading over drain field |
Sept 15 - final grading, rear |
Sept 18 - Lavatory counter tops/sinks installed |
Sept 18 - tile grouted |
Sept 20 - tinted stucco |
Sept 20 - tinted stucco |
Sept 21 - tinted stucco |
Sept 21 - Templates for Kitchen counter tops |
Sept 21 - form for concrete drive, parking/turn around area & walk to (rear) entry |
Sept 21 - form for concrete drive |
Sept 21 - Dad looks over the front porch |
Sept 21 - dig out palm root ball at front steps |
Sept 21 - front yard ready for final grading (Once the dumper goes away) |
Sept 22 - grading for driveway |
Sept 23 - driveway forming at "The Drive" |
Sept 23 - forming turnouts & pull off area @ mailbox |
Sept 25 - pull off area @ mailbox formed |
Sept 26 - placing concrete drive |
Sept 26 - placing concrete drive |
Sept 26 - placing concrete drive |
Sept 26 - finishing parking & turn around area & walk to (rear) entry |
Sept 27 - Kitchen pass-thru counter top |
Sept 28 - Kitchen counter tops |
Sept 28 - Bath specialties, Bath #2 Shower Enclosure/Doors & Grab Bars |
Sept 28 - Bath specialties, Master bath Shower Enclosure |
Sept 27 - Wire shelving installed |
Sept 28 - Steps at front porch (poured with driveway) |
Sept 28 - Screen in, front porch |
Sept 29 - Bath specialties Adjustable shower wand & mirror installed Bath #2 |
Sept 29 - Bath specialties Adjustable shower wand & mirror installed Master Bath |
Sept 29 - FP&L "Hotting up" the meter |
Sept 29 - FP&L "Hotting up" the meter |