Construction Calendar

on our New House

- 27 July 2000 - 11 April 2002

SEPTEMBER 2000
58 - 

Days - 30, WE Days - 9 (Sch'd WE Work Days + 4), Holidays - 1, Available Days - 24, Work days - 24,
Lost Work Days - 0, Inspection Days - 0

SUNDAY
MONDAY
TUESDAY
WEDNESDAY
THURSDAY
FRIDAY
SATURDAY
   
1
Wall Prep
Tile Prep
Elec. Trim
Work Day-64
2
Tile Work
Work Day-65
3
Labor Day
4
Holiday-3
5
Tile Work
Work Day-66
6
Stucco Prep
Work Day-67
7
Stucco Work
Tile Work
Elec Trim
Work Day-68
Sch'd Compln
DATE
8
Stucco Work
Tile Work
Elec Trim
Driveway prep
Work Day-69
Late Compln
week +1
9
Stucco Work
Work Day-70
10
11
Blow Insul.
Elec Trim
Water Lines
Work Day-71
12
Stucco Finish (N&W)
Install Cab's
Work Day-72
13
Grout Bath Tile
Elec Trim
Work Day-73
14
Asphalt removal
Septic T&DF install
Work Day-74
15
Septic T&DF
Rough Grade
Work Day-75
Late Compln
week +2
16
Finish Doors
Work Day-76
17
30 Day Power for Testing Inspection
REJECTED
18
Plumbing Trim
Marble Work
Tile Work
Elec Trim
Shelving
Work Day-77
19
Elec Trim
Work Day-78
20
Stucco Work
completed
Misc. Carpentry
Work Day-79
21
Driveway Form
Counter Top
"Template"
Work Day-80
NEW
Target Compl'n Date
(as of 8/11)
22
Final Grade
Driveway
(backend)
Work Day-81
Late Compln
week +3
23
Driveway form
(front end)
Work Day-82
24
30 Day Power for Testing Inspection 
APPROVED
Driveway
PrePour
Inspection
APPROVED

25
Cabinet
& Marble Work
Work Day-83

26
Driveway
Placement
Ba2 Shower
Curb Cap

Work Day-84

27
Driveway
Placement
Counter Tops
Wire Shelving
Shower Encosures
Plumbing Trim

Work Day-85

28
Front Porch
Screen-in

Work Day-86

29
Gale - mirrors
Tryon - Plumbing Trim

FP&L
Reconnect Svc.

Work Day-87

Late Compln
week +4
30

LOTS OF PICTURES ... Then again, a LOT finally "came together" this month !!


Sept 2 - Tile setting, Entry Foyer

Sept 2 - Tile setting, Kitchen & Dining Nook

Sept 2 - Tile setting, Kitchen

Sept 7 - Electrical "Trim", Installed Lights
1st up - the Ships Wheel Chandelier, salvaged from Dad & Mom's house
(from "nearly" the same position)

Sept 7 - Electrical "trim", Installed ceiling fans & lights

Sept 7 - Stucco, "scratch coat"

Sept 7 - Tile setting, Bath 2

Sept 7 - Tile setting, Master Bath

Sept 8 - Stucco, scratch coat

Sept 8 - stucco, scratch coat
(& electrical conduit runs to Garage & Storage Shed) 

Sept 11 - plumbing, run supply from well

Sept 11 - plumbing, run supply from well

Sept 11 - plumbing, run supply from well

Sept 13 - Kitchen cabinets hung

Sept 13 - Kitchen cabinets hung

Sept 11 - Electrical trim, outside lights

Sept 11 - Electrical trim, meter box & main disconnect

Sept 14 - remove old asphalt drive

Sept 14 - deliver septic tank

Sept 14 - driveway removal

Sept 14 - set septic tank1

Sept 14 - driveway removal

Sept 14 - driveway removal

Sept 14 - septic drainfield installation

Sept 15 - septic drain field installation

Sept 15 - septic drain field installation

Sept 15 - grading over drain field

Sept 15 - final grading, rear

Sept 18 - Lavatory counter tops/sinks installed

Sept 18 - tile grouted

Sept 20 - tinted stucco

Sept 20 - tinted stucco

Sept 21 - tinted stucco

Sept 21 - Templates for Kitchen counter tops

Sept 21 - form for concrete drive, parking/turn around  area
& walk to (rear) entry

Sept 21 - form for concrete drive

Sept 21 - Dad looks over the front porch

Sept 21 - dig out palm root ball at front steps

Sept 21 - front yard ready for final grading
(Once the dumper goes away)

Sept 22 - grading for driveway

Sept 23 - driveway forming at "The Drive"

Sept 23 - forming turnouts & pull off area @ mailbox

Sept 25 - pull off area @ mailbox  formed

Sept 26 - placing concrete drive

Sept 26 - placing concrete drive

Sept 26 - placing concrete drive

Sept 26 - finishing parking & turn around area
& walk to (rear) entry

Sept 27 - Kitchen pass-thru counter top 

Sept 28 - Kitchen counter tops

Sept 28 - Bath specialties, Bath #2
Shower Enclosure/Doors & Grab Bars

Sept 28 - Bath specialties, Master bath
Shower Enclosure

Sept 27 - Wire shelving installed

Sept 28 - Steps at front porch
(poured with driveway)

Sept 28 - Screen in, front porch

Sept 29 - Bath specialties
Adjustable shower wand & mirror installed
Bath #2

Sept 29 - Bath specialties
Adjustable shower wand & mirror installed
Master Bath

Sept 29 - FP&L
"Hotting up" the meter

Sept 29 - FP&L
"Hotting up" the meter

Home | Const Diary